Highway 1 Soquel to Morrissey Auxiliary Lanes

Description: The project will add northbound and southbound auxiliary lanes between Soquel Ave and Morrissey Blvd.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Cruz
City Live Oak, Santa Cruz
Zip Code 95062
 
Senate District
11
Assembly District 27
Congressional District 17
 
Caltrans District
05
 
 
County/State Route Santa Cruz 1
Postmile Begin/End 14.8 16.1
Project Benefits
 Benefit Baseline Actual
Additional Auxiliary Lane Miles  2      
Daily Travel Time Savings (hours)  796    880  
Lane Miles Added (Mixed)      2  
Peak Period Time Savings (minutes)  53893    88300  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Santa Cruz County Regional Transportation Commission Sarah Christensen (831) 460-3204   schristensen@sccrtc.org
Design (PS&E) Phase
Santa Cruz County Regional Transportation Commission Sarah Christensen (831) 460-3204   schristensen@sccrtc.org
Right of Way Phase
Caltrans Luis Duazo (805) 542-4678   luis_duazo@dot.ca.gov
Construction Phase
Santa Cruz County Regional Transportation Commission Sarah Christensen (831) 460-3204   schristensen@sccrtc.org
 
Corridor System Management Plan
Caltrans Claudia Espino (805) 549-3640   claudia.espino@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $2,150 $2,150
CMIA
$16,190 $-2,407 $13,783
Non-bond Funding
State/Federal*
$2,734 $-2,212 $522
Local**
$3,134 $1,496 $4,630
Non Budgeted ETC
$0 $0 $0
 
Total**** $22,058 $-973 $21,085

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,134 $1,233 $2,367 $2,177
Design(PS&E)
$1,960 $-670 $1,290 $1,167
Right of Way
$624 $-129 $495 $381
Construction
$18,340 $-1,407 $16,933 $15,933
 
Total* $22,058 $-973 $21,085 $19,658

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/01/2007 

06/01/2009 
 

 
09/24/2008 

09/18/2009 
100  09/24/2008 

09/18/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/01/2008 

06/01/2010 
 

 
10/15/2009 

05/01/2011 
100  10/15/2009 

06/22/2011 


-2 
Begin Right of Way Phase

End Right of Way Phase
06/01/2009 

03/01/2010 
 

 
09/18/2009 

12/01/2010 
100  09/18/2009 

06/22/2011 


-7 
Begin Construction Phase

End Construction Phase
09/01/2010 

09/01/2012 
 

 
11/01/2011 

11/01/2013 
100  01/05/2012 

02/11/2015 
-2 

-16 
Begin Closeout Phase

End Closeout Phase
10/01/2012 

04/01/2013 
 

07/31/2017 
12/01/2013 

12/01/2014 
100  02/12/2015 

03/25/2021 
-15 

-77 
Corridor System Management Plan
Adoption Date 09/01/2010    09/01/2010  95  08/01/2011  -11 
Implementation Date 10/01/2010    10/01/2010  09/01/2011  -11 
????????
Project Benefits
Benefit Baseline Actual
Additional Auxiliary Lane Miles 2
Daily Travel Time Savings (hours) 796 880
Lane Miles Added (Mixed) 2
Peak Period Time Savings (minutes) 53893 88300

Bond Funding Cost
Adopted:
$16,190,000
Current Approved:
$13,783,000
Actual Expenditures:
$13,783,000

 

Status as of December 31, 2023.